M62 Junction 25 to Junction 30 Managed Motorway Scheme: Overnight Weekend Motorway Closures

M62 Junction 25 to J30 managed motorway Scheme

Installation of 36 new gantries and refurbishing 16 existing gantries between junction 25 and junction 30, from March 2012 to November 2012.

The first closure is scheduled for overnight on Saturday 17th March 2012 for the installation of the first 2 gantries and will be between junctions 27 and 28.

The closures will commence at 8pm in the evening and will be lifted by 8am the following morning. The closures will be approximately every other weekend.

For more details and email updates please Click here……

Diversion Map
M62 Construction of Managed Motorway Scheme

Please bring this information to the attention of your friends and neighbours who may not have access to the internet.

What do you think?

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s