M62 Junction 25 to J30 managed motorway Scheme
Installation of 36 new gantries and refurbishing 16 existing gantries between junction 25 and junction 30, from March 2012 to November 2012.
The first closure is scheduled for overnight on Saturday 17th March 2012 for the installation of the first 2 gantries and will be between junctions 27 and 28.
The closures will commence at 8pm in the evening and will be lifted by 8am the following morning. The closures will be approximately every other weekend.
For more details and email updates please Click here……